You are here: Home » Projects » A40 Pencraig

A40 Pencraig

Project Details

Category
Highway Construction
Client
Highways Agency on behalf of Electricity Alliance
Value
£917,000
Period
10 weeks


The Brief

The works involved constructing duct crossings below the existing A40 dual carriageway. Crossovers were constructed to provide a contraflow Traffic Management system at each end of the scheme. The works used large proprietary trench support systems and considerable concrete backfill for thermal dissipation of the high voltage cables running through the ducts. Both sides were constructed under very tight timescales due to the high impact the works had on the A40 and were completed on time.

360 Images

Looking for a Civil Engineering Contractor for your next project?
Call us now on 01905 350053