St Richards Hospice

Project Details

Category
Drainage
Client
St Richards Hospice through Speller Metcalfe Ltd
Value
£200,000.00 over 2 phases
Period
24 weeks


The Brief

Installing new drainage works which facilitates better existing drainage from the Berryhill village. Works included a welded stormwater system which was proposed by Walsh Construction to offer the Client a saving and to allow a shorter Contract duration. Storm water system incorporated 600 dia concrete pipes which were placed within tight working room and narrow road carriageways. Works were completed within timescales and to the satisfaction of residents affected.